Sand Box John

Aug 04, 2014 

Jan 20, 2014 
 

Dulles Corridor Metrorail Project Construction Progress January 19, 2014

The contractor charged with installing and testing the train control and system signaling system is expected to be done in the first weeks of February. At that time MWAA will hand the project over to WMATA. WMATA will do the final testing and certification that is scheduled to take 90 days. After certification the first […]

Sep 21, 2013 
 

Dulles Corridor Metrorail Project Construction Progress September 15, 2013

Testing continues along the branch. Finishing work on the stations is for all intensive purposes done. There is a number of punch lists items that I noticed that need to be done that will not have any effect on the opening of the line. Such as connecting the entrance pavilion downspouts to the drain pipes. […]